You have given a lease of life to FCT,” Tinubu hails Wike for sterling infrastructure deployment

Published

on

By Kayode Sanni-Arewa

President Bola Tinubu hailed the Minister of the Federal Capital Territory (FCT), Nyesom Wike, for restoring life to the nation’s Federal Capital Territory.

President Tinubu, who spoke on Tuesday when he inaugurated the Southern Parkway from Christian Centre to Ring Road One, a project that started 13 years ago, also said completion of the project was a mark of his commitment to inclusive and sustainable development.

The President, who headed to the inauguration site on arrival from Lagos, identified that the newly inaugurated road, which the FCT administration named after him, would not only ease traffic congestion, but also enhance mobility and creativity for the residents and visitors to city.

Advertisement

“But transformative projects you are seeing, I heard from his remark that this project could have been an abandoned project for 13 years, scratching the surface. Once again, our dear landlord, Barrister Ezenwo Nyesom Wike, thank you for bringing life back to our Federal Capital Territory.

I understand the Southern Parkway not only represents a physical artery that connects vital areas within FCT, but also symbolises our collective aspirations for connectivity, ease of livelihood, accessibility and progress.

“By providing a seamless and efficient transportation corridor, this road will not only ease traffic congestion, but also enhanced mobility and creativity for the residents and visitors to FCT.

“The completion of the Southern Parkway underscores our, as we strive to build a world-class capital city. We recognise the fact that infrastructure is an enabler of jobs, economic development and prosperity. We believe we are going to achieve all of that.

Advertisement

“The needs of our citizens is paramount in our minds, so for making our citizens the central focus of our development, we believe Nigeria will succeed. As we formally inaugurate this road, I am greatly honoured, I heard him mentioning my name as the beneficiary. Thank you very much; thank you for being a very good team leader, we all collectively will not let you down,” the President said.

He lauded the FCT Minister, Wike, for his vision and hard work, which he said had effected changes, both structurally and administratively, to the capital and has inspired many citizens.

“I must recognise your vision that is revolutionary and very inspiring to many of our people. The changes you made to the FCT – structural and administrative – is yielding results and elevating the heart of many Nigerians, thank you very much.

“Today, we are here to mark a significant milestone in the journey of our nation towards progress and development. As we commemorate our first year in office when I was inaugurated as the President of the Federal Republic of Nigeria, it is a great joy and challenge that we have a huge job on our…, “ he said.

Advertisement

Wike said the projects had dragged on for several years.

However, he said the coming of the current administration and President’s unflinching support had led to the completion of the project amongst others, that are ready for inauguration.

He said the FCTA and the FCT Residents appreciated Tinubu’s support and laudable achievements.

He said: “It is in this regard and for many other patriotic persuasions that the FCT Administration hereby humbly resolved that this very important road be named the “BOLA AHMED TINUBU WAY”.

Advertisement

The Minister said the Southern Parkway was one of the principal arteries conceived and planned as a freeway to provide access and connectivity to the Southern development flank of the city as provided in the Abuja Master Plan.

He said other principal artery was the Northern Parkway which had been substantially developed over the years to service the Northern districts.

According to Wike: “Southern Parkway at par with the Northern Parkway, this project which was awarded in December, 2010 to Messrs Setraco Nig. Ltd. at the contract sum of N16,234,553,335.64 (Sixteen billion, Two Hundred and Thirty-Four Million, Five Hundred and Fifty-Three Thousand, Three Hundred and Thirty-Five Naira, Sixty Four Kobo).

“Later it was revised to N35,757,763,310.18 (Thirty-Five Billion, Seven Hundred and Fifty-Seven Million, Seven Hundred and Six-Three Thousand, Three Hundred and Ten Naira, Eighteen Kobo) in March, 2021 due to changes in scope and other economic indices.

Advertisement

“The scope of work comprised the construction of 5.4km length of the road – made up of 2 main carriageways of 4 lanes each and 2 service carriageways of 2 lanes each, making a total of 12 lanes.

“It also includes the construction of 4 number Interchanges (a total of 8 bridges) in addition to the provision of associated underground engineering infrastructure facilities.

“I am happy to further inform your Excellency that the project is now completed in line with the “Renewed Hope Agenda” of Mr. President. The completion of the project will indeed enhance traffic circulation around the City Centre thereby reducing delays in travel time; complementing the developed portion of the Northern Parkway by easing the traffic congestion experienced in the Southern Districts of Garki, Gudu, and Durumi as well as accelerating the development of the Southern axis of the city in general, thereby bringing improved socio-economic benefits to residents and visitors to the city.

“Your Excellency, Distinguished Ladies and Gentlemen, on assumption of office in August 2023 we were confronted with many uncompleted projects that have dragged on for several years.” [with report by The Nation]

Advertisement
Continue Reading
Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

News

FG announces April deadline for completion of East-West Road

Published

on

By

The Federal Government has directed the contractor handling the Eleme section of the East-West Road to expedite drainage work to meet the April deadline for completion.

The Minister of Works, David Umahi, issued the directive during an inspection of the ongoing 15km road upgrade from Eleme Junction to Onne in Eleme Local Government Area of Rivers State.

While commending Reynolds Construction Company Nigeria Limited for the quality of work done, Umahi insisted that the drainage must be prioritised to ensure timely completion.

“RCC has done very well. The work completed in the past two months is more than what was done since the project started. However, the project slowed down significantly when the site manager went on leave. I’m happy to see him back and satisfied with the quality of work RCC is delivering,” Umahi stated.

Advertisement

He emphasised the need to test existing road shoulders before excavation, warning against unnecessary digging for financial gains.

“The existing shoulder has to be tested throughout. I don’t want them digging up areas filled with sharp sand and stone base just to increase costs. If they don’t test it and request approval for any section they dig, they won’t get paid,” he warned.

Umahi also observed that drainage construction had either stopped or slowed significantly, urging the contractor to redesign and precast drainage systems for quicker installation, even during the rainy season.

“I’m happy with the project’s progress, and I believe they will complete the carriageway by the end of April. However, if drainage work is not completed, the project remains unfinished. They must accelerate drainage work to ensure we clear this carriageway by April,” he stated.

Advertisement

The minister further directed that any section of the road that has remained untouched for 21 days after concrete casting should be opened to commuters to ease traffic congestion.

“Anywhere that has stayed 21 days since concrete was cast should be opened to road users, starting today. This concrete technology will ensure the road lasts between 50 and 100 years without maintenance or reconstruction. It is a signature project of President Bola Tinubu,” he added.

Umahi also inspected the rehabilitation of the Enugu-Port Harcourt dual carriageway, Section IV (Aba–Port Harcourt), which is being handled by the Chinese Construction Engineering Company.

Advertisement
Continue Reading

News

Reasons behind extreme heat conditions in FCT, Niger, Kogi – NiMet

Published

on

By

The Nigerian Meteorological Agency (NiMet) has given reasons for the high temperatures residents of the Federal Capital Territory (FCT), Niger, Kogi and few other states are currently experiencing.

The current maximum temperature in the listed states is 40°C and the minimum is 23°C.

The Seasonal Climate Prediction (SCP) released last month by the agency shows that most of the northern and central states would record day-time temperatures ranging between 37°C and 40°C, while parts of Kano, Kaduna, Bauchi, and Plateau states in the North as well as Oyo, Osun, Ogun, Ekiti, Edo, Enugu, Anambra, Ebonyi, Imo, Abia, part of Cross River and Delta states in the South are expected to record temperatures ranging between 34°C and 37°C this month.

The agency attributed the high temperatures to climate change and advised Nigerians to embrace a lifestyle switch.

Advertisement

Residents of the states experiencing high temperatures are advised to avoid exposure to direct sunlight between noon and 3 p.m.

There are also indications that this year may be hotter than last year, which was described as the hottest year.

NiMet’s Director of Weather Services, Prof. Vincent Weli, announced this while speaking on phone with The Nation yesterday. He said: “Everything is embedded in the climate change theory. Every experience we are having now is a result of climate change. The hotness, in general, is because of climate change.

“Abuja, Lokoja, and Minna are located within the same ecological zone and these towns share the same weather pattern. Whatever happens to Lokoja will affect Minna and Abuja because they are in the same route of the flow of wind and also lie within the same climatic zone. Also, these towns have the same vegetation pattern.

Advertisement

“So, since they are within the same climatic belt, everything that affects Minna and the FCT will affect Lokoja accordingly. The heat is affecting everywhere, not just these towns mentioned. We said last year was the hottest in the history of the earth but this year already is trying to beat it to become the hottest.

“So, as the year increases, it’s obvious that we are going to have higher temperatures. I don’t know where we are headed with this trend, but something needs to be done to reverse the trend.”

To make the best of the situation, Prof. Weli said: “What can reverse the trend is for us to encourage every activity of man that will reduce the emission of carbon dioxide into the atmosphere, such as the use of electric cars, solar power and planting of trees.

“These will be other sources of energy other than the use of diesel and petrol and other hydrocarbon compounds that we use as sources of power. Also, we should plant more trees to reduce carbon dioxide in the atmosphere. The more we plant trees, the more we reduce carbon dioxide in the atmosphere and the more we increase the oxygen.”

Advertisement

The NiMet director urged residents of the affected states with high temperatures to take necessary action to overcome the hot weather.

He said: “In order not to experience what we call heat stroke, people should drink more water often, keep themselves off the direct impact of sunlight between 12 p.m (noon) and 3 p.m. If people do not expose their bodies to the direct impact of sunlight, it will reduce water loss from the system.

“So, people should drink more water than necessary. Otherwise, their systems will be dehydrated, and that will cause secondary health issues.”

Advertisement
Continue Reading

News

JAMB begins sales of  2025 direct entry forms March 12

Published

on

By

Registration for this year’s Direct Entry (DE) form will begin tomorrow, the Joint Admissions and Matriculation Board (JAMB) has said.

The board said the registration process is crucial for those who possess degrees, diplomas, or A-Level certificates and wish to advance their education at their preferred universities.

JAMB’s Public Communications Advisor, Dr. Fabian Benjamin, announced this in a statement yesterday in Abuja.

The statement said the announcement for the commencement of the DE sales followed the successful conclusion of the Unified Tertiary Matriculation Examination (UTME) application sales, which ended on Saturday, March 8.

Advertisement

“During this period, JAMB recorded a total of 2,030,627 registrations for the 2025 UTME, along with 200,115 for the Mock-UTME and 630 applications for the trial mock,” the statement said.

It added: “JAMB has emphasised the importance of adhering to all entry requirements, warning that serious penalties will be imposed on applications containing false declarations. A special committee will verify all submitted Advanced A-Level Qualifications, and any fraudulent results will lead to prosecution. Additionally, institutions are encouraged to directly verify certificates before considering admissions.

“Registration can only be done at JAMB Professional Registration Centres (PRC).”

Advertisement
Continue Reading

Trending

Copyright © 2024 Naija Blitz News